Contract A Incentives/Disincentives
underline image

Contract A

I-10 from Harris/Fort Bend County Line to East of Peek Road (SH 99)
Bid Amount $83 Million
Total Project Duration 921 days

Incentives/Disincentives
Milestone Milestone Duration (Days) * Max. Days Allowed for Early Completion

Daily
Incentive Amount

Daily
Disincentive Amount
Milestone Started Milestone Completed Monetary Value

Milestone 1: Close/reopen partial SH 99 frontage road underpass.

37

10

($50,000 per day for 10 days)
Maximum $500,000

($50,000 per day)

02/11/2005

03/03/2005

$500,000**

Milestone 2: Beginning of project to opening of SH 99 underpass and I-10 U-turns; cross-traffic on SH 99 in final configuration and detour for Mason Rd closure completed.

628

0

N/A

($20,000 per day)

09/18/2003

07/07/2005

N/A

Milestone 3: Westbound mainlanes traffic shift to proposed pavement throughout project limits.

821

100

($25,000 per day for 100 days)
Maximum $2,500,000

($20,000 per day)

09/18/2003

12/17/2005

$2,500,000**

Milestone 4: Final Acceptance; Traffic in final configuration.

921

0

N/A

($5,000 per day)

09/18/2003

11/20/2006

N/A

* Does not include weather delays, time-suspensions, float-days or holidays. Calculation is based on contractors’ work days not actual calendar days.
** Incentive earned by contractor.
*** Disincentive assessed to contractor.