Traffic Control Plan (TCP).
The TCP is divided into phases and steps. Listed below is a description of each phase and step of construction to be accomplished. See the Plans for additional information.
Phase 1 - Step 1
- Install advance warning signs.
- Remove existing railroad bridges.
- Install SW3P devices.
- Construct portion of outfall structure at STA 1287+37 and westbound frontage road storm sewer system.
- Construct proposed roadway illumination along westbound frontage road.
- Construct permanent westbound frontage road from STA 1281+00 to STA 1363+00 and from STA 1383+50 to STA 1395+00 excluding SH 6 intersection. Provide a leave out at the existing Metro T-ramp.
- Construct the proposed entrance and exit ramps. Leave openings for uninterrupted traffic at side streets, and clearance at the column of the Addicks Park & Ride T-ramp structure.
- Construct temporary ramps PH1R1, PH1R2, PH1R4, PH1R5 & PH1R6 with temporary cross culverts.
Phase 1 - Step 1A
- Shift westbound frontage road traffic to temporary ramps PH1R1, PH1R2. Construct westbound frontage road from STA 1275+00 to STA 1281+00.
- Construct temporary pavement at medians along SH 6 as shown.
Phase 1 - Step 2
- Install advance warning signs.
- Close westbound frontage road thru traffic at SH 6.
- Shift SH 6 two-way traffic onto existing northbound lanes.
- Construct temporary and permanent paving and temporary drainage at the intersection as shown.
- Place temporary striping for lane configuration to be used in Phase1 Step 3.
- Shift westbound frontage road traffic to new westbound frontage road west of SH 6.
Phase 1 - Step 3
- Install advance warning signs, no access to SH 6 and thru traffic from westbound frontage road.
- Shift SH 6 two-way traffic to pavement constructed in Phase 1 Step 2.
- Construct temporary and permanent paving and temporary drainage at the intersection.
- Restripe SH 6 pavement to pre-construction lane configuration. Open to traffic.
- Shift westbound frontage road traffic to new westbound frontage road from STA 1363+00 to west. Use temporary ramp PH1R6 for detour frontage road traffic from existing westbound frontage road to new westbound frontage road.
- Contractor shall install all permanent small signs along new westbound frontage road as per permanent signing layout unless they are in conflict with the remaining construction.
Phase 2 - Step 1
- Westbound frontage road traffic is on newly constructed westbound frontage road lanes.
- New temp ramps PH1R4 and PHIR5 are open.
- Construct temp u-turn at SH 6.
- Construct remaining westbound frontage road storm sewer system.
- Construct westbound frontage road from STA 1363+00 to STA 1383+50 excluding Eldridge Parkway intersection.
- Construct westbound mainlane pavement from STA 1321+54 to STA 1328+07 and STA 1345+46 to STA 1355+50.
- Construct temporary ramp PH21R1 and PH21R2.
- Construct temporary drainage and ditch.
- Section 6 contractor to construct temporary pavement for westbound mainlanes detour from Section 7 to Section 6 and proposed pavement from STA1392+60 to STA 1395+00.
- Construct temporary pavement at medians along Eldridge Parkway as shown.
Phase 2 - Step 1a
- Install advance warning signs, no access to westbound frontage thru traffic and westbound frontage road access from Eldridge Parkway.
- Close westbound frontage road thru traffic at Eldridge Parkway.
- Shift Eldridge Parkway two-way traffic onto existing northbound lanes.
- Construct temporary and permanent paving and temporary drainage at the intersection as shown.
- Place temporary striping for lane configuration to be used in Phase 2 Step 1B.
- Shift westbound frontage road traffic to new westbound frontage road from Eldridge Parkway to west.
Phase 2 - Step 1B
- Install advance warning signs, no access to Eldridge Parkway from westbound frontage road and westbound frontage road thru traffic at the Eldridge Parkway.
- Shift Eldridge Parkway two-way traffic to pavement constructed in Phase 2 Step 1A.
- Construct temporary and permanent paving, and temporary drainage at the intersection.
- Restripe pavement to Eldridge Parkway pre-construction lane configuration. Open to traffic.
- Westbound frontage traffic is completely shifted to new westbound frontage.
- Contractor shall install all permanent small signs along new westbound frontage road as per permanent signing layout unless they are in conflict with the remaining construction.
Phase 2 - Step 2
- Install advance warning signs. Close existing ramps and open new temp ramp PH21R1 and PH21R2 constructed in Phase 2 Step 1.
- Transition mainlanes traffic at the beginning of the project as shown.
- Construct temp u-turn at Eldridge Parkway.
- Construct the westbound mainlanes from STA 1275+00 to STA 1321+54, STA 1328+07 to STA 1345+45, and STA 1355+50 to STA 1392+60. This work includes construction of the westbound bridges at SH 6, Langham Creek and Eldridge Parkway.
- Leave out 24'x30' around an existing column of the existing Metro T-ramp from STA 1314+49 to STA 1314+79.
- Construct permanent and temporary drainage structures.
- Construct the temporary pavement inside of exist eastbound frontage road from STA 1275+00 to STA 1299+50 with temporary shoring as shown.
Phase 3 - Step 1
IH-10 mainlanes
- Shift the existing westbound IH-10 traffic from the existing lanes to the new westbound right-most three lanes constructed in Phase 2, Step 2.
- From sta. 1275+00 to STA 1395+00, begin construction of remaining westbound mainlanes and part of eastbound mainlanes.
- Construct temporary and permanent drainage structure.
- Construct new elevated HOV lane structure including Park & Ride ramp, leave out two spans at the existing turn-table structure.
- Construct temporary on-ramp for the eb traffic at STA 1339+07 to STA 1348+38.
- Construct temporary eastbound mainlane off-ramp from STA 1297+84 to STA 1314+37.
- Construct temporary eastbound cross-over from STA 1345+00 to STA 1357+00. Finish this on the weekend with HOV closed and shift the traffic for Phase 3 Step 2 right after that.
- Section 6 contractors to construct temporary pavement for eastbound mainlanes detour from Section 7 to Section 6.
- Construct the eastbound storm sewer system and outside proposed frontage road from STA 1276+90 to STA 1296+63.
Phase 3 - Step 1
Park and Ride lot
- Construct managed lanes, exit and entrance ramps, bridges, retaining walls, pavement, etc. In the following sequence.
- Remove existing pavement from STA 10+00 to STA 21+92.
- Construct permanent drainage from STA 10+00 to STA 21+92.
- Construct toll lane access ramp bridge, walls BB, CC, and GG, and permanent pavement.
- Construct exit and entrance ramp bridges. Existing Park & Ride driveway to be detoured to west most lanes during bent construction at STA 27+00.
- Construct embankment, retaining walls EE, FF after Metro's contractor has completed traffic circulation to the proposed driveway at STA 25+30.
Phase 3 - Step 2
- Install advance warning signs and channelization devices.
- Shift eastbound mainlane traffic onto the inside lane of the new westbound IH-10 mainlanes at approximate STA 1345+00 to STA 1357+00.
- Shift Park & Ride traffic from the existing Metro T-ramp to the new Metro T-ramp. New elevated HOV structure to provide access eastbound and westbound from and to Park & Ride only (no thru movements west of Park & Ride on this structure).
- Shift the HOV traffic from its existing location to the westbound mainlane pavement.
- Open new eastbound temporary ramp constructed in Phase 3 Step 1.
- Demolish the existing Metro T-ramp including columns in the vicinity of STA 1314+50. Turntable to remain.
- Finish construction of the proposed westbound mainlanes in the vicinity of the old T-ramp and from STA 1384+63 to STA 1400+74.
- Shift eastbound frontage road traffic from beginning of project to STA 1296+63 to outside and construct inside frontage road from STA 1276+90 to STA 1296+63.
Phase 3 - Step 3
- Install advance warning signs and channelization devices.
- Demolish and remove existing HOV turntable in the vicinity of the Addicks Park & Ride at STA 1314+71. Freeway to be closed for this operation.
- Demolish and remove existing Langham Creek and Eldridge Parkway bridges.
- Construct permanent and temporary drainage structures.
- Construct the inside half of the proposed eastbound mainlanes between STA 1296+30 and STA 1351+00.
- Construct the eastbound mainlanes from STA 1356+00 to STA 1373+80 including Langham Creek structure.
- Construct remaining two spans of the new elevated HOV structure.
- Begin construction of the eastbound mainlanes retaining walls in the vicinity of Eldridge Parkway.
- Construct the temporary pavement inside of existing eastbound frontage from STA 1315+30 to STA 1352+00 and STA 1360+14 to STA 1395+00.
- Construct the temporary pavement for eastbound frontage road detour PH 33 R1.
Phase 3 - Step 4
- Install warning signs and channelization devices.
- Shift the eastbound mainlanes traffic from their location onto the inside half of the new westbound mainlanes west of SH 6 overpass. Then east of the SH 6 overpass, transition eastbound mainlanes onto the inside half of the new eastbound mainlane pavement, around the Metro T-ramp, and back to the inside half of the westbound mainlane pavement before STA 1345+00. Construct the outside eastbound mainlanes STA 1275+00 to STA 1357+00.
- Use standard TCP(6-4A) for closure of Eldridge Parkway off ramp STA 1304+00. Construct the temporary exit ramp for Eldridge Parkway at STA1315+00 and open within two days.
- Shift eastbound frontage road traffic to inside temporary pavement 1315+30 to STA 1352+00.
- Detour the eastbound frontage road traffic across the eastbound mainlane Langham Creek bridge.
- Demolish the existing mainlane bridges at SH 6 and eastbound frontage road bridge at Langham Creek.
- Construct SH 6 intersection as per SH 6 Phase 4 Steps 1 and 2.
- Finish SH 6 Phase 4 Step 1 and Step 2.
- Construct permanent and temporary drainage structures.
- Complete construction of the eastbound mainlanes from STA1275+00 to STA 1395+00.
- Construct the new eastbound mainlane bridge at SH 6 & Eldridge Parkway.
- Shift SH 6 traffic to north & south frontage road as shown in Phase 4 Step 3 and begin construction of IH10 overpass substructure at IH-10 and SH 6 intersection.
- Construct the outside portion of the proposed eastbound frontage from STA 1321+86.7 to STA 1351+00 and STA 1367+45 to STA 1395+00, and full section from STA 1351+00 to STA 1367+45 including eastbound frontage road bridge at the Langham Creek.
- Construct the temporary pavement inside of existing eastbound frontage road from STA 1296+66 to STA 1314+00.
Phase 3 - Step 5
- Install warning signs and channelization devices.
- Shift eastbound frontage road traffic to inside temporary pavement from STA 1296+66 to STA 1314+00 and outside new eastbound frontage road from STA 1321+86.7 to STA 1395+00.
- Construct permanent and temporary drainage structures.
- Construct the inside portion of the proposed eastbound frontage from STA 1321+85 to STA 1351+00 and STA 1367+45 to STA 1395+00, and outside portion from STA 1296+66 to STA 1314+00.
- Construct outside 26 ft of eastbound frontage road from STA 1275+00 to STA 1276+90.
- Open new exit ramp PH36 R1 and close exist exit ramp at STA 1315+00. Construct outside 26 feet of eastbound frontage road from STA 1314+00 to STA 1321+85. (Phase 3 Step 5A)
Phase 3 - Step 6
- Install warning signs and channelization devices.
- Construct permanent drainage structures.
- Shift eastbound frontage road traffic to new outside eastbound frontage road portion from STA 1296+66 to STA 1321+85.
- Construct the inside portion of the proposed eastbound frontage from STA 1296+66 to STA 1321+85.
- Construct the proposed eastbound mainlanes from STA 1313+06 to STA 1317+24.6
- Close temporary on ramp at STA 1348+00 and open proposed on-ramp at STA 1278+00. Finish proposed on ramp at STA 1348+00. (Phase 3 Step 6A)
Phase 3 - Step 6A
IH-10 eastbound fr ramp
- Install advance warning signs and channelization devices.
- Shift traffic onto south side of eastbound fr.
- Construct permanent drainage structure.
- Construct ramp from eastbound fr to ramp.
Phase 3 - Step 6a
Eldridge Parkway & Vicinity
- Install advance warning signs and channelization devices.
- Shift Eldridge Parkway two-way traffic to southbound lanes.
- Construct permanent drainage structure.
- Construct Eldridge Parkway northbound lanes and u-turn.
Phase 3 - Step 6B
Eldridge Parkway & Vicinity
- Install advance warning signs and channelization devices.
- Close eastbound frontage road on weekend with detour as shown.
- Construct part of eastbound frontage road at Eldridge Parkway using fast track construction.
Phase 3 - Step 6C
Eldridge Parkway & Vicinity
- Install advance warning signs and channelization devices.
- Close eastbound frontage road on weekend with detour as shown.
- Construct remainder of eastbound frontage road at Eldridge Parkway using fast track construction.
Phase 3 - Step 6D
Eldridge Parkway & Vicinity
- Install advance warning signs and channelization devices.
- Shift Eldridge two-way traffic to northbound lanes.
- Construct permanent drainage structure.
- Construct Eldridge Parkway southbound lanes and u-turn.
Phase 4 - Step 1
SH 6 & Vicinity
- Contractor shall begin construction of SH 6 north of IH-10 as soon as soon as verification is received from the engineer for ROW acquisition and utility adjustment. Approximate date of start of construction is in or before October 2006.
- Contractor shall begin construction of SH 6 intersection at IH-10 Phase 3 Step 1 and Step 2.
- Contractor shall begin construction of SH 6 intersection at IH-10 after demolition of existing IH10 bridge in IH-10 Phase 3 Step 4.
- Install advance warning signs and channelization devices.
- Stripe and shift traffic as shown.
- Construct permanent and temporary drainage structures.
- Construct northbound frontage road.
- Construct southbound frontage road north of IH-10.
Phase 4 - Step 2
SH 6 & Vicinity
- Contractor shall begin construction with IH-10 Phase 3 Step 1 and Step 2 and after Phase 4 Step 1.
- Contractor shall begin construction of SH 6 intersection at IH-10 after demolition of existing IH-10 bridge in IH-10 Phase 3 Step 4.
- Install advance warning signs and channelization devices.
- Stripe and shift traffic utilizing part of northbound frontage road south of IH-10.
- Construct permanent and temporary drainage structures.
- Construct southbound frontage road south of IH-10 as shown.
Phase 4 - Step 3
SH 6 & Vicinity
- Install advance warning signs and channelization devices.
- Stripe and shift traffic to northbound and southbound frontage roads
- Construct permanent drainage structures.
- Construct SH 6 mainlanes, embankment, retaining walls, bridge, pavement etc.
- Construct roadway illuminations.
- Install permanent stripes and signs. See striping and signing layout for details.
Phase 4 - Step 3A-B
SH 6 & Vicinity
- Install advance warning signs and channelization devices.
- Stripe and shift traffic to alternate locations.
- Construct pavement at IH-10 eastbound frontage road and SH 6 intersection, and Park Row, Grisby and Memorial at SH 6.
- Install permanent stripes and signs where appropriate. See striping and signing layout for details.
Phase 4 - Step 3C-F
SH 6 at Park Row
- Install all additional signs and channelization devices.
- Stripe and shift traffic to alternate locations.
- Construct remaining pavement at the intersection of Park Row at SH 6.
|