Contract C2 Incentives/Disincentives
underline image

Contract C2

East of Eldridge to East of Kirkwood
Bid Amount $84 Million
Total Project Duration 1,100 days

Incentives/Disincentives
Milestone Milestone Duration (Days) * Max. Days Allowed for Early Completion Daily Incentive Amount Daily Disincentive Amount Milestone Started Milestone Completed Monetary Value

Milestone 1: Complete all work necessary for the switch of I-10 westbound mainlanes and HOV.

301

20

($10,000 per day for 20 days)
Maximum $200,000

($10,000 per day)

04/04/2005

03/04/2006

$200.000**

Milestone 3: Complete all work necessary for the I-10 eastbound mainlane switch for the entire project limits.

319

10

($10,000 per day for 10 days)
Maximum $100,000

($10,000 per day)

03/06/2006

11/11/2006

$100,000**

Milestone 4: Complete all work necessary for the I-10 westbound frontage shift and substantial completion of the project.

251

30

($10,000 per day for 30 days)
Maximum $300,000

($10,000 per day)

06/04/2007

12/21/2007

$300,000**

Milestone 5: Substantial completion of project.

448

30

($5,000 per day for 30 days)
Maximum $150,000

($5,000 per day)

11/13/2006

02/29/2008

$150,000**

Milestone 6: Administrative work to close out project.

1100

0

N/A

$1,650

04/04/2005

03/30/2009

N/A

Interim Milestone 1: Closure and reopening of westbound exit ramp to Kirkwood.

50

10

($5,000 per day for 10 days)
Maximum $50,000

($5,000 per day)

04/23/2007

05/19/2007

$50,000**

Interim Milestone 2: Closure and reopening of westbound exit ramp to Dairy Ashford.

30

10

($5,000 per day for 10 days)
Maximum $50,000

($5,000 per day)

07/08/2007

07/28/2007

$50,000**

* Does not include weather delays, time-suspensions, float-days or holidays. Calculation is based on contractors’ work days not actual calendar days.
** Incentive earned by contractor.
*** Disincentive assessed to contractor.