Contract D
I-10, East of Beltway 8 to East of Kirkwood
Bid Amount $250 Million
Total Project Duration 1351 days
Incentives/Disincentives
| Milestone |
Milestone Duration (Days) * |
Max. Days Allowed for Early Completion |
Daily Incentive Amount |
Daily disincentive Amount |
Milestone Started |
Milestone Completed |
Monetary Value |
Milestone 1: Traffic shift of I-10 westbound mainlane traffic to the completed westbound mainlane pavement. |
307 |
20 |
($30,000 per day for 20 days)
Maximum $600,000 |
($30,000 per day) |
10/04/2004 |
07/31/2005 |
$600,000** |
Milestone 2: Traffic shift of the I-10 METRO HOV lane from existing location to completed westbound mainlane pavement. |
178 |
20 |
($10,000 per day for 20 days)
Maximum $200,000 |
($10,000 per day) |
08/01/2005 |
12/18/2005
|
$200,000** |
Milestone 3: Traffic shift of the I-10 eastbound mainlane to the completed median. |
149 |
20 |
($30,000 per day for 20 days)
Maximum $600,000 |
($30,000 per day) |
12/19/2005 |
03/19/2006 |
$600,000** |
Milestone 4: Completion of all the work as shown on phase 5-4 west of BW8. |
232 |
60 |
($30,000 per day for 60 days)
Maximum $1,800,000 |
($30,000 per day) |
04/03/2006 |
09/30/2006 |
$1,800,000** |
Milestone 5: Opening of the Beltway 8 northbound and southbound flyovers bridges and approaches, including auxiliary lanes, shoulders, in their final configuration. |
404 |
60 |
($10,000 per day for 60 days)
Maximum $600,000 |
($10,000 per day) |
05/04/2005 |
06/27/2007 |
$600,000** |
Milestone 6: Opening of I-10 eastbound and westbound mainlanes including auxiliary lanes and shoulders in the final configuration. |
86 |
25 |
($20,000 per day for 25 days)
Maximum $500,000 |
($20,000 per day) |
|
07/18/2008 |
$500,000** |
Milestone 7: Final inspection and acceptance of the project. |
1401 |
0 |
N/A |
|
10/04/2004 |
Target Date
12/1/2009
|
|
Milestone H: Reopen Connector H to traffic. |
97 |
30 |
($10,000 per day for 30 days)
Maximum $300,000 |
($10,000 per day) |
04/07/2007 |
06/21/2007 |
$300,000** |
Milestone A: Reopen Connector A to traffic. |
219 |
60 |
($20,000 per day for 60 days)
Maximum $1,200,000 |
($20,000 per day) |
04/07/2007 |
09/18/2007 |
$1,200,000** |
Milestone G: Reopen Connector G to traffic. |
204 |
60 |
($10,000 per day for 60 days)
Maximum $600,000 |
($10,000 per day) |
04/20/2007 |
12/01/2007 |
$600,000** |
Milestone B: Reopen Connector B to traffic. |
90 |
30 |
($10,000 per day for 30 days)
Maximum $300,000 |
($10,000 per day) |
10/05/2007 |
12/07/2007 |
$300,000** |
Milestone E: Reopen Connector E to traffic. |
78 |
30 |
($10,000 per day for 30 days)
Maximum $300,000 |
($10,000 per day) |
01/05/2008 |
04/06/2008 |
$300,000** |
Milestone D: Reopen Connector D to traffic. |
196 |
60 |
($20,000 per day for 60 days)
Maximum $1,200,000 |
($20,000 per day) |
01/05/2008 |
08/22/2008 |
$1,200,000** |
Milestone F: Reopen Connector F to traffic. |
204 |
60 |
($20,000 per day for 60 days)
Maximum $1,200,000 |
($20,000 per day) |
05/08/2008 |
08/22/2008 |
$1,200,000** |
Milestone C: Reopen Connector C to traffic. |
117 |
45 |
($10,000 per day for 45 days)
Maximum $450,000 |
($10,000 per day) |
04/07/2008 |
07/11/2008 |
$450,000** |
* Does not include weather delays, time-suspensions, float-days or holidays. Calculation is based on contractors’ work days not actual calendar days.
** Incentive earned by contractor.
*** Disincentive assessed to contractor.
|