Image: Curve Decoration
Image: Katy Freeway Building our Future logo
Image Link: Program Overview
Image Link: Program Timeline
Image Link: Newsroom
Image Link: Lane Closures / Updates
Image Link: Frequently Asked Questions
Image Link: Submit Your Feedback / Contact Us
Image Link: Visit Our Sitemap
Image Link: Return to Katy Freeway Home Page

Contract E1 Incentives/Disincentives
underline image

Contract E1

From East of Beltway 8 to east of Campbell
Bid Amount $204 Million
Total Project Duration 1,186 days

Incentives/Disincentives
Milestone Milestone Duration (Days) * Max. Days Allowed for Early Completion Daily Incentive Amount Daily Disincentive Amount Milestone Started Milestone Completed Monetary Value

Milestone 1: Complete all work necessary for the I-10 westbound mainlane switch.

254

30

($60,000 per day for 30 days)
Maximum $1,800,000

($60,000 per day)

03/01/2005

10/29/2005

$1,800,000**

Milestone 2: Complete all work necessary for the HOV switch.

53

20

($10,000 per day for 20 days)
Maximum $200,000

($10,000 per day)

10/31/2005

12/08/2005

$200,000**

Milestone 3: Complete all work necessary for the I-10 eastbound mainlane switch.

319

10

($30,000 per day for 10 days)
Maximum $300,000

($30,000 per day)

01/02/2006

12/11/2006

$300,000**

Milestone 4: Complete all work necessary for the new I-10 westbound frontage road.

405

20

($20,000 per day for 20 days)
Maximum $400,000

($20,000 per day)

06/04/2007

06/30/2008

$400,000**

Milestone 5: Complete all Interim Striping  (Substantial Completion).

518

40

($60,000 per day for 40 days)
Maximum $2,400,000

($60,000 per day)

12/08/2006

06/30/2008

$2,400,000**

Milestone 6: Administrative work to close out project.

1186

0

N/A

$1,650

03/01/2005

Target Date
08/01/2009

 

Interim Milestone A: Close/reopen the I-10 eastbound Gessner Entrance Ramp.

77

30

($10,000 per day for 30 days)
Maximum $300,000

($10,000 per day)

11/12/2007

01/04/2008

$300,000**

Interim Milestone B: Close/reopen the I-10 eastbound Blalock Entrance Ramp

27

10

($10,000 per day for 10 days)
Maximum $100,000

($10,000 per day)

10/27/2007

11/07/2007

$100,000**

Interim Milestone C:
Close/reopen the I-10 westbound Blalock Entrance Ramp.

62

20

($10,000 per day for 20 days)
Maximum $200,000

($10,000 per day)

05/30/2008

05/31/2008

$200,000**

Interim Milestone D: Close/reopen the I-10 westbound Gessner Exit Ramp.

23

15

($10,000 per day for 15 days)
Maximum $150,000

($10,000 per day)

06/07/2008

06/07/2008

$150,000**

Interim Milestone E: Complete all work necessary for the I-10 eastbound Frontage Road west of Gessner.

20

10

($10,000 per day for 10 days)
Maximum $100,000

($10,000 per day)

11/05/2007

04/13/2008

$100,000**

Early completion

7/31/2008

 

$2,500,000

 

 


$2,500,000**

* Does not include weather delays, time-suspensions, float-days or holidays. Calculation is based on contractors’ work days not actual calendar days.
** Incentive earned by contractor.
*** Disincentive assessed to contractor.



[Katy Freeway [Program Overview] [Program Timeline] [Newsroom] [Lane Closures] [FAQs] [Feedback] [Sitemap]

Image: TxDOT Logo and Copyright 2007