Contract G
East of IH 610 to West of Washington
Bid Amount $43 Million
Total Project Duration 438 days
Incentives/Disincentives
| Milestone |
Milestone Duration (Days) * |
Max. Days Allowed for Early Completion |
Daily Incentive Amount |
Daily Disincentive Amount |
Milestone Started |
Milestone Completed |
Monetary Value |
Milestone 1: Construction of temporary Union Pacific Railroad bridge. |
162 |
0 |
NA |
($30,000 per day) |
03/05/2007 |
09/23/2007
|
NA |
Milestone 2: Traffic shift of I-10 eastbound and westbound mainlanes to their final configuration. |
251 |
30 |
($30,000 per day for 30 days)
Maximum $900,000 |
($30,000 per day) |
10/22/2007 |
06/28/2008 |
$900,000** |
Milestone 3: Administrative milestone from start of project to final completion. |
438 |
0 |
NA
|
($2,000 per day) |
03/05/2007 |
Target Date 08/06/2008 |
|
Interim Milestone A: Construction of permanent Union Pacific Railroad bridge. |
96 |
0 |
NA |
($30,000 per day) |
10/22/2007 |
02/08/2008 |
NA |
Interim Milestone B: Closure and reopening of the eastbound entrance ramp from Washington. |
47 |
20 |
($5,000 per day for 20 days)
Maximum $100,000 |
($5,000 per day) |
04/07/2008 |
04/30/2008 |
$100,000** |
* Does not include weather delays, time-suspensions, float-days or holidays. Calculation is based on contractors’ work days not actual calendar days.
** Incentive earned by contractor.
*** Disincentive assessed to contractor.
|