Construction Packages
underline image

Graphic of Katy Freeway

Construction
Package

Contract
A

Contract
B

Contract
C1

Contract
C2

Contract
D

Contract
E1

Contract
E2

Contract
F

Contract
G

Description

Ft. Bend
County Line
to E of Peak

E of Peek
to W of SH 6

W of SH 6
to E of Eldridge

E of Eldridge
to E of
Kirkwood

E of Kirkwood
to E of BW 8

E of BW 8
to E of
Campbell

E of Campbell
to E of Silber

E of Silber to
E of IH 610 &
Interchange

E of IH 610
to W of
Washington

Proposed Letting
Date

7/2003

5/2003

3/2005

12/2004

7/2004

1/2005

2/2005

7/2003

1/2007

End of
Construction

7/2006

6/2006

9/2008

8/2008

10/2008

9/2008

10/2008

5/2007

8/2008

Construction Cost
Estimate

$83 Million**

$208 Million**

$153 Million**

$84 Million**

$250 Million**

$204 Million**

$158 Million**

$263 Million**

$43 Million**

 


** Actual Bid Amount.


Vegetative Landscaping and Final
Signing/Striping for Toll lanes will be
awarded as separate contracts.

Revised November 5, 2008